PRE-MANUFACTURING SERVICES
The provision of pre-manufacturing cable systems for under floor
installations reduces installation time and cost. Cables are measured,
labelled, terminated and tested at both ends, the looms are either
put onto drums or shrink wrapped prior to delivery to site. Cables
can be loomed or bundled dependent on the requirements of the manufacturer's
installation procedures. All cables are totally traceable as to
their length, test results, floor box and patch panel details.
Once delivered to site the cables are installed and retested to
guarantee the complete integrity of the installation. On-site test
results are compared with the original factory test results to ensure
their traceability is maintained. All test results and as installed
drawings are provided to the customer on CD-ROM.
During the project Stoneleigh can provide full batch traceability
from each cable loom and project managers can use the system to
produce site installation sheets to track the following stages:
• looms received on-site
• looms installed
• box end fitted
• cabinet end installed
• installation visually inspected
• installation tested
• witness tested by customer if appropriate
Using this technique a team of 5 on-site can typically install,
test and handover about 1000 outlets per day. This represents a
significant reduction in installation time and brings real benefits
and cost savings to the customer. Pre-manufacturing requires the
detailed analysis up front to determine cable lengths, outlet numbers,
box numbers and cabinet layouts therefore it is only viable for
structured cabling systems of over 500 outlets. To date Stoneleigh
have been involved with the installations ranging from host cable
swap outs from CAT5 to CAT6 up to complete CAT6 structured cabling
systems in excess of 30,000 UTP is connections.
|